Section 48D’s 35% Credit Expires December 31: The Equipment Timing Problem Behind the Tax Deadline

  1. Confirm the facility-level question first. Is the facility’s primary purpose semiconductor or semiconductor equipment manufacturing? Everything else is downstream of that answer.
  2. Map basis item by item. Which tools are integral, which are on contiguous parcels, which have original use commencing with the taxpayer, and what the total cost of each unit of property is – the 5 percent test is computed per unit, not per project.
  3. Pick a beginning-of-construction route and document it. Physical work of a significant nature, or 5 percent paid or incurred. Preliminary activities and unsigned proposals do not establish either.
  4. Start the continuity file now. Continuous construction or continuous efforts has to be demonstrable across years, not reconstructed in 2031.
  5. Do not let a tax date dictate an unqualified install. Utilities, exhaust, chemical approval, FAT/SAT, and first-article qualification all take calendar time. A tool installed early and qualified late costs more than a tool ordered on a sensible schedule.

Akrivis supports U.S. and North American manufacturers building domestic electronics and semiconductor process capability – cleaning and contamination control, vapor degreasing, lead forming and cutting, legacy component reconditioning, tinning and solderability, wire bonding, and thermal and vacuum process equipment, with application support in North America. We do not provide tax or legal advice, and we make no representation that any particular piece of equipment qualifies for Section 48D, Buy American, or any other program; those determinations rest on the taxpayer’s facts and counsel’s analysis. What we can do is help a process team define the residue, the chemistry, the profile and the qualification evidence before the equipment is specified – which is the part of the schedule nobody quotes.

If a 2027 line is on your capital plan, request an application review and we will work through the process requirements with your engineers.

Sources

Standards referenced: IPC-TM-650 2.3.25 (ionic contamination), J-STD-002 (solderability), ASTM E595 (outgassing), MIL-STD-883 methods 2011 and 2019 (bond pull and die shear).

There are eight weeks left on the calendar for one of the largest capital incentives in U.S. semiconductor manufacturing. Under Section 48D of the Internal Revenue Code, the advanced manufacturing investment credit pays 35 percent of the qualified investment in property that is part of an advanced manufacturing facility – a facility whose primary purpose is manufacturing semiconductors or semiconductor manufacturing equipment. The credit does not apply to property whose construction begins after December 31, 2026.

That is a statutory fact, not a forecast. Congress has not extended it. On August 5, Senate Finance Chairman Mike Crapo and Ranking Member Ron Wyden issued a joint statement supporting extension (Thomson Reuters), and two bipartisan bills are pending – the SEMI Investment Act, S. 1642 / H.R. 6055, which would extend the credit through 2031 and add materials integral to semiconductor manufacturing, and the Semiconductor Superiority Act, S. 4750 / H.R. 8959. Two weeks ago TechNet wrote to congressional leaders asking for a clean multi-year extension (letter, October 19). SEMI has run two separate advocacy pushes this year on the same deadline (SEMI, @SEMIconex), and SIA plus 17 other trade groups did the same in May (@SIAAmerica). None of that is a statute.

The commercial consequence is already visible. On October 1, Bloomberg reported that TSMC is weighing a multi-fab Texas campus that would only proceed if Congress extends the credit before it sunsets (Maggie Eastland, Bloomberg). A company that has already committed $265 billion to Arizona is treating a tax provision as a gating condition on the next $20 billion-per-fab decision. That is what a planning cliff looks like from the inside.

The deadline tests the start of construction, not the end of the project

The single most common misreading of Section 48D is that a facility has to be finished, or the tool placed in service, by year-end. It does not. Section 48D(e) denies the credit based on when construction begins. The final regulations at 26 CFR 1.48D-5 give two alternative routes to establish that date:

  • Physical work test. Construction begins when physical work of a significant nature starts on the property, followed by continuous construction or continuous efforts. There is no minimum dollar threshold, but the work has to be significant – a foundation, concrete pads, structural work. Off-site work counts when it is performed under a binding written contract entered into before manufacture begins, and the work is on property for the taxpayer rather than on the vendor’s standard inventory.
  • Five percent safe harbor. Construction is treated as begun when the taxpayer pays or incurs at least 5 percent of the total cost of the property and then maintains continuous construction or continuous efforts. Cash-method taxpayers look to amounts paid; accrual-method taxpayers look to amounts incurred.

Two exclusions in Holland & Knight’s October analysis are worth reading twice. Preliminary activities do not count, no matter how much they cost or how carefully they are capitalized: planning, design, financing, research, permitting, surveys, environmental and engineering studies, and site clearing. And simply signing a contract is not enough – actual qualifying physical work must begin. A December purchase order, on its own, is neither. A December purchase order with a 5 percent payment against it may be, if the basis and the accrual treatment are documented.

Once construction has begun in 2026, the continuity rule is generous: the regulations provide a 10-calendar-year safe harbor, so property that begins construction this year and is placed in service by December 31, 2036 is deemed to satisfy continuity. Miss that window and continuity becomes a facts-and-circumstances argument. There is also a 10-year recapture period for significant transactions involving the property.

Where the money actually sits: the tools

Qualified property under Section 48D is tangible, depreciable property – constructed or acquired with original use commencing with the taxpayer – that is integral to the operation of the advanced manufacturing facility. The regulations define integral narrowly and usefully: used directly in the manufacturing operation, essential to the completeness of that operation, and not materially transformed by it. The preamble example is an air separation unit supplying nitrogen on demand.

Read that against a packaging or device line and the basis is obvious. Cleaning and contamination-control lines, vapor degreasing, plasma and wet benches, solderability and tinning stations, die attach and wire bonding, vacuum reflow and thermal process equipment, lead forming and trim tools, and the metrology that proves any of it works – all of it sits directly in the manufacturing operation and none of it is consumed by it. For a project already in planning, the equipment package is usually the largest single block of basis after the building shell.

There is also a contiguity rule that changes site plans. Property does not have to be inside the walls of the facility or even on the same tax parcel. It can sit on a contiguous parcel – parcels separated only by a road, rail line, utility corridor or stream still count – provided the property is qualified property and integral to the operation. Support equipment placed across the street is not automatically out of scope, and equipment parked on the site but not integral is not automatically in.

The scope gate most suppliers get wrong

Section 48D is not a general domestic manufacturing credit. The facility’s primary purpose must be manufacturing semiconductors or semiconductor manufacturing equipment. An EMS provider doing SMT assembly for industrial, medical and defense customers is, in the ordinary case, not an advanced manufacturing facility under this section even if a semiconductor customer’s product runs down the same line. A tool supplier building process equipment for fabs is. A materials refiner is not, which is precisely why the SEMI Investment Act proposes adding materials integral to semiconductor manufacturing to the definition.

The practical result is three different answers for three companies on the same industrial park, and a lot of suppliers being told by someone that “you’re covered.” That determination belongs with tax counsel and the taxpayer’s own facts. It is not something to infer from a press release, and it is not something an equipment vendor should assert on a customer’s behalf.

Why this becomes a process engineering problem in January

If a meaningful share of Q4 tool orders are pulled forward to preserve a 2026 construction start, the installation and qualification load lands in the first half of 2027 – compressed, on new lines, often in facilities whose utilities are still being commissioned. That is where the credit gets spent badly.

The failure modes are unglamorous and predictable:

  • Chemistry selected before the residue is characterized. A cleaning process specified against “no-clean flux” in general rather than against the actual paste, reflow profile and component mix will pass incoming inspection and fail ionic contamination testing later. IPC-TM-650 2.3.25 ionic contamination and non-volatile residue testing exist because “looks clean” is not a specification.
  • Vapor degreasing converted without a solvency and materials review. Solvent transitions change elastomer compatibility, stencil and adhesive performance, and waste streams. The equipment is rarely the constraint; the qualification evidence is.
  • Solderability assumed from incoming lot history. Legacy and long-lifecycle components – the exact parts that domestic DDR4, defense and aerospace programs depend on – oxidize in storage. J-STD-002 solderability testing and a defined reconditioning route are cheaper than a reworked assembly, and much cheaper than a line-down event on a program with no second source.
  • Thermal and vacuum processes commissioned against a datasheet instead of a profile. Vacuum bake-out, reflow and bonding profiles have to be developed on the actual product with the actual fixturing, then held under continuous verification. For space and defense hardware, ASTM E595 outgassing and MIL-STD-883 bond pull and shear (methods 2011 and 2019) are the evidence, not the oven’s setpoint log.
  • Traceability built after the fact. A 35 percent credit on a tool that cannot produce a defensible process record – lot, chemistry, profile, operator, calibration – is a discount on a liability. The record is what survives an audit, a customer survey or a government source inspection.

None of that is a reason to slow down. It is a reason to sequence differently: book the application engineering and the qualification lots at the same time the purchase order is issued, not after the tool lands. Equipment lead time is visible on a quote. Qualification time is not, and it is the one that moves the production date.

A short checklist before December 31

  1. Confirm the facility-level question first. Is the facility’s primary purpose semiconductor or semiconductor equipment manufacturing? Everything else is downstream of that answer.
  2. Map basis item by item. Which tools are integral, which are on contiguous parcels, which have original use commencing with the taxpayer, and what the total cost of each unit of property is – the 5 percent test is computed per unit, not per project.
  3. Pick a beginning-of-construction route and document it. Physical work of a significant nature, or 5 percent paid or incurred. Preliminary activities and unsigned proposals do not establish either.
  4. Start the continuity file now. Continuous construction or continuous efforts has to be demonstrable across years, not reconstructed in 2031.
  5. Do not let a tax date dictate an unqualified install. Utilities, exhaust, chemical approval, FAT/SAT, and first-article qualification all take calendar time. A tool installed early and qualified late costs more than a tool ordered on a sensible schedule.

Akrivis supports U.S. and North American manufacturers building domestic electronics and semiconductor process capability – cleaning and contamination control, vapor degreasing, lead forming and cutting, legacy component reconditioning, tinning and solderability, wire bonding, and thermal and vacuum process equipment, with application support in North America. We do not provide tax or legal advice, and we make no representation that any particular piece of equipment qualifies for Section 48D, Buy American, or any other program; those determinations rest on the taxpayer’s facts and counsel’s analysis. What we can do is help a process team define the residue, the chemistry, the profile and the qualification evidence before the equipment is specified – which is the part of the schedule nobody quotes.

If a 2027 line is on your capital plan, request an application review and we will work through the process requirements with your engineers.

Sources

Standards referenced: IPC-TM-650 2.3.25 (ionic contamination), J-STD-002 (solderability), ASTM E595 (outgassing), MIL-STD-883 methods 2011 and 2019 (bond pull and die shear).